10/08/2024 | Press release | Distributed by Public on 10/08/2024 12:11
What's coming up in the construction process this spring?
We are moving into the final stages of construction for the project. The fire pit is nearing completion, as are the North and South patios. Landscape plantings are going in, and, and work on window weatherproofing will wrap up over the next few months. New building entrances have been installed, and Library Dr / Vresics Walk will be uncovered over the next month.
New developments
After calling for community feedback, we are pleased to share the names of the retail dining locations coming to the Clayton University Center. Follow dining on social media for information about food samplings at the flagpole throughout the fall semester and an opportunity to share your feedback!
Lower Eatery
The Crossing
Upper Eatery
The third floor will house the Lehigh Pub
Vision:
Current progress:
- Upper floors are nearing completion, including the Lehigh Pub, Great Room, and Boardroom spaces
- Kitchen equipment installation is ongoing throughout building
- The new South Entry glass curtain wall and louver have been installed
- Building controls are complete and systems are coming online for testing and commissioning over the next few weeks
- Audio visual and furniture installation to begin in late October
Vision:
Current progress:
- Fire pit is nearly complete
- Concrete for NE accessible entrance poured
- Landscaping has started in key areas
- Reimagined LEHIGH letters pad will be completed in early November
- South Entry installation milestone with curtain wall and louver installed
- East lot - prepping for generator pad and new paving