Alameda County - Caltrans is temporary suspending work for the Capital Preventive Maintenance project on Interstate 880 (I-880) between the City of Fremont and Santa Clara County. This project will extend pavement life and enhance ride quality along 90 lane miles. The project spans 11.8 miles in each direction along I-880, from Fremont Boulevard south to the Alameda County/Santa Clara County line, touching key sections in Fremont and Newark. This comprehensive project includes asphalt replacement, ADA-compliant curb ramp upgrades, installation of pedestrian flashing beacons, guardrail upgrades, loop detector replacements, and improvements to traffic systems and signage.
Project Update: Paving Suspension Due to Weather
Due to anticipated low temperatures and potential rain, which would impact paving quality, Caltrans will temporarily suspend paving operations on I-880 from November 13, 2024, through Spring 2025. Paving is expected to resume April 2025.
Both northbound and southbound lanes of I-880 have been fully paved and permanently striped from Dixon Landing Road to Mowry Avenue. Paving between Mowry Avenue and Alvarado Boulevard remains and is projected to finish by the end of summer 2025, weather permitting. Full project completion is scheduled for the end of 2025.
Be Work Zone Alert and expect travel delays.
Caltrans will update its X page at https://twitter.com/CaltransD4on the latest highway conditions, and drivers are encouraged to check out Caltrans Quickmap http://quickmap.dot.ca.gov/
Motorists can also receive 24/7 highway condition information statewide by calling 1-800-427-ROAD or 1-800-427-7623.
For project website click here.