11/22/2024 | Press release | Distributed by Public on 11/22/2024 15:00
Began earthwork in median from Herky Horine Road to north of Route Z. Began excavation for and construction of retaining walls for I-55 bridge over Herky Horine Road. Continued work on drilled shaft foundations for I-55 bridge over Joachim Creek. Drove pile and formed and poured intermediate bent for I-55 bridge over McNutt. Set girders for the I-55 bridge over McNutt and placed deck panels, began placing bridge deck rebar. Continued concrete paving in I-55 median and on sections of US 67.